RAE and UT Quality Complete Subsea Tieback Work in the Penn State Deep (DSP) Field in the GOM
Overview
In June of 2017, RAE was awarded a contract from McDermott to jointly provide subsea tieback work in the Penn State Deep (PSD) field in the Gulf of Mexico for a major oil and gas exploration company. Penn State Deep 6 has been developed as a subsea tieback to the Baldpate facility.
The 5,189 foot, 8.625-inch-OD flowline system was fabricated onshore at the McDermott Gulfport Spoolbase and then reeled on its North Ocean 105 lay vessel to be completed and installed to a water depth of about 1,650 feet.
RAE was responsible for providing full-service project management of the flowline and tie-in system, extending to spoolbase pipe fabrication and handling, and offshore services, including NDT and FJC of the flowline and welding of the tie-in PLET structure aboard the lay vessel.
The project was completed and online by March of 2018.
Hess Baldpate facility offshore in the Gulf of Mexico.
Scope of Work
Project Management
- Onsite Supervision 
- Trained and Certified Personnel 
- Materials & Equipment Management 
- Firing Line Productivity 
- QHSE 
Welding
- Manual Welding (TIG) of 8.625-in of Flowline Stocks at Spoolbase 
- Manual Welding (TIG/SMAW) of Tie-In PLET Structure on Vessel 
Inspection by UT Quality
- AUT utilizing proprietary UT Scan PA System on Vessel 
Field-Joint Coating
- Blast 
- Induction Heating 
- Application of FBE, CMPP, & IMPP 
- Technical Services 
Pipe Handling Operations
- Pipe Receipt and Offloading 
- Roller Boxing 
- Spooling Operations 
Results
Production Rates
- Welded 11 joints per day on 130 joints 
Repair Rates
- 1 weld repair 
Daily Manning Levels
- 68 welding and coating personnel 